March Update

3 Forge Lane, Welwyn

We are pleased with progress at the site on Forge Lane. Externally, the rendering has been completed and the scaffold has been dropped. Ground workers will return to finish the drainage and adjust the external space ready for paving to be placed. Internally the dry lining has been completed to Plot 1 and has just commenced to Plot 2. Despite the wet weather we have had over the winter months we are not too far behind the build programme.

11 Wendover Lodge, Welwyn

Construction has recently begun at the top of Church Street. This development will consists of 2 detached homes with separate entrances and garages. Both plots are currently available with a guide price of £685,000.

The foundation brick and block work has been completed to Plot 1 and the block and beam slab has been laid by our ground workers. The bricklayers have returned to site to commence the foundation brick and block work to Plot 2.

Please contact us for the opportunity to look at the latest drawings and elevations.